Proof of Concept · Executive Brief

Air-to-Ground Connectivity Proof of Concept

SkyFive Arabia × Airline — Air-to-Ground Connectivity. A focused 24-week program to validate SkyFive A2G performance on a single Airline Airbus in KSA airspace.

24

weeks

Total Duration

5

milestones

Project Phases

35

activities

Tracked Tasks

1

Airbus

Aircraft

Five Milestones at a Glance

1

Project Initiation & Alignment

Weeks 15

8 activities

2

Engineering & Regulatory Preparation

Weeks 619

6 activities

3

Material & Logistics

Weeks 414

9 activities

4

Installation & Integration

Weeks 2022

7 activities

5

Flight Trial & Customer Experience

Weeks 2224

5 activities

Ground Network

Ground network will use KSA infrastructure

All air-to-ground connectivity leverages the existing, operational SkyFive/STC ground network in KSA — no new ground build-out required for the POC.

Live · KSA

Project Timeline · 24 Weeks

W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
1. Project Initiation & Alignment
1.1Introduce SkyFive A2G Solution
1.2Airline Executive Alignment Meeting
1.3Confirm POC Objectives & Success Criteria
1.4Select Airbus Aircraft for POC
1.5Confirm KSA Airspace for Flight Trials
1.6Select MRO (Airline M&E Preferred)
1.7Logistics and Customs Alignment
1.8Technical Coordination Meeting (ITCM)
2. Engineering & Regulatory Preparation
2.1Aircraft Technical Survey
2.2Aircraft Survey Report
2.3Installation Design Review (PDR/CDR)
2.4Modification Package Review (STC/SB)
2.5Local Aviation Authority Coordination
2.6Initial Readiness Review (IRR)
3. Material & Logistics
3.1OBE Equipment Reservation (Thales)
3.3Cabin Server & CWAP Allocation (Kontron)
3.4Installation Kit Allocation (Eclipse)
3.5Secure Import License for POC Equipment
3.6Confirm HS Codes & Customs Requirements
3.7Shipment Preparation
3.8Transportation to Egypt
3.9Customs Clearance
3.10Material Inspection & Storage
4. Installation & Integration
4.1Aircraft Grounding Window Confirmation
4.2Aircraft Modification & Installation
4.4System Power-On & Functional Check
4.5EMI Testing
4.6End-to-End Integration Testing
4.7Regulatory Inspection
4.8Return to Service (RTS)
5. Flight Trial & Customer Experience
5.1Flight Testing in KSA Airspace
5.2KPI Validation (Coverage, Throughput, Latency)
5.3Stakeholders Experience Survey
5.4POC Performance Report
5.5Executive Go / No-Go Meeting

Key Recommendations

Considerations to keep the POC fast, low-cost and low-risk.

1

Single Airline Airbus Aircraft

Use one Airline Airbus aircraft only for the entire POC to minimise cost, scheduling complexity and grounding time.

Lower cost · Simpler logistics
2

Validate in KSA Airspace

Perform all flight validation in KSA airspace where SkyFive/STC A2G infrastructure already exists and is operational today.

Infrastructure ready now
3

Airline M&E as Installation MRO

Use the Airline's Maintenance & Engineering as the installation MRO to leverage in-house capability and reduce coordination overhead.

In-house capability
4

Front-load Customs & Regulatory

Secure customs and regulatory approvals during the first month to remove the longest-lead-time risk from the critical path early.

De-risks critical path
5

Reuse SkyFive/STC Certification

Reuse existing SkyFive/STC certification packages wherever possible to dramatically reduce approval and engineering time.

Faster approvals